This work presents an alternative MILP mathematical formulation for the short-term scheduling of pipeless batch plants based on a continuous-time representation that relies on the general precedence notion. Besides of the intrinsic characteristics of a pipeless plant, this model considers the moveable vessels as an additional resource that has to be allocated and sequenced. This fact allows proposing a strategy consisting of a sequential treatment of the resources to reduce the complexity of th...
This work presents an alternative MILP mathematical formulation for the short-term scheduling of pipeless batch plants based on a continuous-time representation that relies on the general precedence notion. Besides of the intrinsic characteristics of a pipeless plant, this model considers the moveable vessels as an additional resource that has to be allocated and sequenced. This fact allows proposing a strategy consisting of a sequential treatment of the resources to reduce the complexity of the problem.
Ver más
Ver menos
Palabras Clave
Pipeless plantsScheduling